* Cluster first: build renewable profiles and add all assets after clustering * [pre-commit.ci] auto fixes from pre-commit.com hooks for more information, see https://pre-commit.ci * correction: pass landfall_lengths through functions * assign landfall_lenghts correctly * remove parameter add_land_use_constraint * fix network_dict * calculate distance to shoreline, remove underwater_fraction * adjust simplification parameter to exclude Crete from offshore wind connections * [pre-commit.ci] auto fixes from pre-commit.com hooks for more information, see https://pre-commit.ci * remove unused geth2015 hydro capacities * removing remaining traces of {simpl} wildcard * add release notes and update workflow graphics * [pre-commit.ci] auto fixes from pre-commit.com hooks for more information, see https://pre-commit.ci --------- Co-authored-by: pre-commit-ci[bot] <66853113+pre-commit-ci[bot]@users.noreply.github.com> Co-authored-by: lisazeyen <lisa.zeyen@web.de>
625 B
625 B
1 | Unit | Values | Description | |
---|---|---|---|---|
2 | p_max_pu | -- | Value in [0.,1.] | Correction factor for link capacities ``p_nom``. |
3 | p_nom_max | MW | float | Global upper limit for the maximum capacity of each extendable DC link. |
4 | max_extension | MW | float | Upper limit for the extended capacity of each extendable DC link. |
5 | length_factor | -- | float | Correction factor to account for the fact that buses are *not* connected by links through air-line distance. |
6 | under_construction | -- | One of {'zero': set capacity to zero, 'remove': remove completely, 'keep': keep with full capacity} | Specifies how to handle lines which are currently under construction. |